In hardware, the schedule is the supply chain

"Two weeks" in hardware means two weeks after the parts arrive. Put lead times on your plan before you promise a date.

2 min readDeep techRisk

The joke founders recognise

“How long will it take?”

Software: “Two weeks.” Hardware: “Two weeks after the parts arrive.”

It’s funny because it’s true. In software, the work is most of the schedule. In hardware, much of the schedule is waiting for things other people make.

How long the wait can be

Y Combinator’s latest Requests for Startups gives a sense of scale for the AI buildout. Large power transformers have a three-year lead time. Switchgear, circuit breakers and liquid cooling equipment are sold out. The grain-oriented electrical steel used in transformer cores is made in a single plant in the US.

Robots have the same problem. YC notes that China made 94% of the world’s sintered rare-earth magnets in 2024, and when it restricted exports in April 2025, some automakers had to cut production.

What it means for your plan

Your critical path doesn’t run through your team alone. It runs through your suppliers, their suppliers and the shipping in between. A plan that only counts engineering time will be wrong, and investors who’ve backed hardware before will know it.

The calendar is a competitor

Parts are only one queue. Launch slots, wafer runs and grid connections are booked months or years ahead, and they don’t move because your round closed. In deep tech, the calendar is a competitor. Book the slow slots first.

Where it goes wrong

  • Single-source parts. One supplier, one delay, and the whole build waits.
  • Ordering after the design freeze. The long-lead parts should be identified, and ideally reserved, while the design is still moving.
  • Quoting build time as delivery time. Tell investors and customers when it ships, not when you’ll finish your part.

Try it this week

  1. List every part with a lead time longer than four weeks.
  2. Find a second source for the riskiest one, or a design change that removes it.
  3. Redo your timeline with lead times in it, and use that date from now on.

Sources

  1. Y Combinator, Requests for Startups (Data Center Supply Chain; Robots Made in America)