Bent Flyvbjerg studied more than 16,000 big projects.
Bent Flyvbjerg studied more than 16,000 big projects.
8.5% hit time and budget.
0.5% hit time, budget and the promised benefits.
His rule: think slow, act fast.
Most projects do the opposite. They rush the plan, then get stuck in delivery, where every change is slow and expensive.
Plan slowly and cheaply: models, simulations, prototypes. Changing a drawing costs almost nothing. Changing steel costs a fortune.
Then build fast. The longer delivery takes, the more can go wrong. Source: Flyvbjerg and Gardner, How Big Things Get Done.